Projects
Schedule of District Facility Projects:
- Phase 1: Adams Elementary, Harrison Elementary, Jefferson Elementary, Lincoln Elementary, Van Buren Elementary, Washington Elementary
- Phase 2: Edison Middle School, Jackson Elementary, Madison Elementary, Marshall Middle School, Monroe Elementary, Parker High School, Wilson Elementary
- Phase 3: Craig High School, Kennedy Elementary, Franklin Middle School, Rock River Charter, Roosevelt Elementary
2021 D&P= Design & Preconstruction B= Bidding C= Construction |
||||||||||||
Jan. | Feb. | Mar. | Apr. | May | June | July | Aug. | Sept | Oct. | Nov. | Dec. | |
Phase 1 | D&P | D&P | D&P | B | B | C | C | C | ||||
Phase 2 | D&P | D&P | D&P | D&P | B | B | C | C | C | |||
Phase 3 | D&P | D&P | D&P | D&P | B |
2022 D= Design & Preconstruction B= Bidding C= Construction |
||||||||
Jan. | Feb. | Mar. | Apr. | May | June | July | Aug. | |
Phase 1 | ||||||||
Phase 2 | C | C | C | C | C | |||
Phase 3 | B | C | C | C |
Construction at Washington Elementary School:
Photos taken Friday, July 2, 2021
Work begins on the Washington entryway, as part of the Secure Pathways Project.
Construction at Jefferson Elementary School:
Photos taken Friday, July 2, 2021
Work begins on the Jefferson entryway, as part of the Secure Pathways Project.
Construction at Adams Elementary School:
Photos taken Friday, July 2, 2021
Work begins on the Adams entryway, as part of the Secure Pathways Project.
Construction at Lincoln Elementary School:
Photos taken Wednesday, June 30, 2021
Work begins on the Lincoln outdoor drop-off area and the indoor entryway, as part of the Secure Pathways Project.
Groundbreaking Ceremony:
Tuesday, May 25, 2021
More of a "Wall Smashing" Ceremony - Lincoln Elementary School hosted an event to signify the commencement of referendum-funded District Facility Projects. Lincoln Elementary is one of the 6 SDJ schools that will see construction in the first of three phases of the Secure Pathways Project. (See graphic at top of page.)
Lincoln Elementary students and members of School District of Janesville Leadership & School Board put on their hard hats and smashed the symbolic wall.
Dr. Shawn Galvin (Principal of Lincoln Elementary School), Steve Pophal (Superintendent of Schools), and Greg Ardrey (School Board Treasurer) addressed attendees with words of gratitude and excitement for projects to begin. Members of the School District of Janesville and Janesville media representatives were present.
Thank you to JP Cullen & EUA for your work organizing this event!
Dr. Shawn Galvin (Principal of Lincoln Elementary School), Steve Pophal (Superintendent of Schools), and Greg Ardrey (School Board Treasurer) addressed attendees with words of gratitude and excitement for projects to begin. Members of the School District of Janesville and Janesville media representatives were present.
Thank you to JP Cullen & EUA for your work organizing this event!
Bid Day:
Thursday, April 29, 2021
Janesville area businesses bid on projects associated with District Facility Updates.
Pre-Bid Meeting/Tours of SDJ Facilities:
Monday, April 19, 2021
While JP Cullen (Construction Management Firm) & EUA (Architecture Firm) are contracted to take on most of the District Facility projects, they will receive bids from Janesville area businesses for smaller facets of projects such as flooring, windows, plumbing, etc.
Pictured are members of The School District of Janesville, JP Cullen, and EUA guiding representatives from Janesville area businesses (potential bidders) through a tour of SDJ Facilities to show first-hand the work that needs to be done.