Between March of 2020 and 2021, Congress passed three stimulus bills under the Elementary and Secondary School Emergency Relief Fund (ESSER) with allocations of funding for school districts. ESSER funding is one time funding to allow districts to prevent, prepare for, and respond to COVID-19. Funding was available to address facilities projects dealing with indoor air quality and social distancing improvements.
Franklin Middle School
The work to improve indoor air quality (IAQ) at Franklin is a two-year project that started construction in June of 2023 with an anticipated completion date of September 1, 2024.
JP Cullen serves as the project’s construction manager and EUA as the project’s architect.
New duct work in tunnels under pool mechanical room.
New hydronic piping (glycol heating) with insulation jackets and labeling in tunnels under Franklin MS.
550 Ton truck crane picking old LMC roof top air handler off the roof.
550 Ton truck crane preparing to pick up new chiller and set into place on the equipment pad to the East of of the pool.
550 Ton Truck Crane with Boom Extended, Preparing to pick old Roof Top Air Handler off LMC Roof
2 Existing main boilers in the process of being converted from operation on steam to glycol solution
New Air Handler Unit in Pool Mechanical Room
550 Ton truck crane picking and swinging old LMC roof top air handler off the building.
Greenhouses
The two main high school greenhouses were selected to be replaced to improve social distancing and educational adequacy. JP Cullen serves as the project’s construction manager and EUA as the project’s architect. The Parker project will start construction May 2024 and the Craig project will start in June 2024. Both projects are anticipated to be completed by September 1, 2024.
Photos of Craig High School
Photos of Parker High School